[1]薛青松,林永亮,周忠群,等.考虑承压水地连墙穿越粉砂层槽壁稳定性分析[J].华南地震,2022,(01):119-126.[doi:10.13512/j.hndz.2022.01.16]
 XUE Qingsong,LIN Yongliang,ZHOU Zhongqun,et al.Trench Stability Analysis of Artesian Water Underground Diaphragm Wall Passing Through Silty Sand Layer[J].,2022,(01):119-126.[doi:10.13512/j.hndz.2022.01.16]
点击复制

考虑承压水地连墙穿越粉砂层槽壁稳定性分析()
分享到:

华南地震[ISSN:1006-6977/CN:61-1281/TN]

卷:
期数:
2022年01期
页码:
119-126
栏目:
土木工程防震减灾
出版日期:
2022-03-30

文章信息/Info

Title:
Trench Stability Analysis of Artesian Water Underground Diaphragm Wall Passing Through Silty Sand Layer
文章编号:
1001-8662(2022)01-0119-08
作者:
薛青松1林永亮2周忠群2张 雪2
1.中铁二十局集团第一工程有限公司,江苏 苏州 215151;2.上海大学力学与工程科学学院,上海 200444
Author(s):
XUE Qingsong1LIN Yongliang2ZHOU Zhongqun2ZHANG Xue2
1.China Railway 20th Bureau Group First Engineering Co.,Ltd.,Suzhou 215151, China;2.School of Mechanics and Engineering Sciences , Shanghai University , Shanghai 200444, China
关键词:
地下连续墙粉砂层承压水极限平衡稳定性安全系数
Keywords:
Diaphragm wall Silty sand layer Artesian water Limit equilibrium Safety factor of stability
分类号:
TU473.2
DOI:
10.13512/j.hndz.2022.01.16
文献标志码:
A
摘要:
地下连续墙在成槽施工中粉砂层特别容易发生局部失稳现象,针对粉砂层在承压水作用的出现失稳破坏问题,通过建立粉砂层三维滑动体稳定性分析模型,基于极限平衡原理,提出槽壁稳定性安全系数计算公式,并结合实际工程案例进行理论验证分析以及槽壁稳定性影响因素分析。研究结果表明:提出的粉砂层槽壁稳定性安全系数计算公式基本是可靠的,可为后续粉砂层地连墙施工提供一些理论参考;通过槽壁稳定性影响因素分析,承压水和地下水位是造成粉土夹砂层槽壁失稳破坏的最主要原因,泥浆液面深度和泥浆重度对槽壁稳定性影响较大,相比之下,地面附加荷载对槽壁稳定性影响较小。
Abstract:
The silt layer is particularly prone to local instability in the construction of underground diaphragm wall. Aiming at the instability and failure of silt layer under the action of artesian water, a three-dimensional sliding body stability analysis model of silt layer is established. Based on the principle of limit equilibrium,a formula for calculating the safety factor of trench wall stability is proposed, and the theoretical verification analysis and analysis of the influencing factors of trench wall stability are carried out combining with actual engineering cases. The research results show that the proposed formula for calculating the safety factor of the stability of the trench wall of the silty sand layer is basically reliable, which can provide some theoretical references for the subsequent construction of the silty sand layer diaphragm wall; based on the analysis of the influencing factors of the trench well stability, it is found that artesian water and groundwater level are the main reasons for the instability and failure of the trench well in silty sand layer. The slurry depth and mud weight have a greater impact on the stability of the trench well, while the additional load on the ground has a smaller impact on the stability of the trench well.

参考文献/References:

[1] Britto A M,Kusakabe O. Stability of unsupported axisymmetric excavations in soft clay[J]. Geotechnique,1982,32(3):26.
[2]姜朋明,胡中雄,刘建航.地下连续墙槽壁稳定性时空效应分析[J].岩土工程学报,1999(03):3-5.
[3]张厚美,夏明耀.地下连续墙泥浆槽壁稳定的三维分析[J].土木工程学报,2000(01):73-76.
[4]王轩,雷国辉,施建勇.矩形地连墙槽壁整体稳定分析方法的对比研究[J].岩土力学,2006(04):549-554+560.
[5]丁勇春,李光辉,程泽坤,等.地下连续墙成槽施工槽壁稳定机制分析[J]. 岩石力学与工程学报,2013,32(S1):2704-2709.
[6]陈孟红.地下连续墙局部与整体稳定性分析[J].公路工程, 2013,38(04):218-221.
[7] Han C Y,Chen J,Wang J H,et al. 2D and 3D stability analysis of slurry trench in frictional-cohesive soil[J]. Journal of Zhejiang University-Science A,2013,14(2):94-100.
[8] Han C Y,Wang J H,Xia X H,et al. Limit analysis for local and overall stability of a slurry trench in cohesive soil[J]. International Journal of Geomechanics,2015,15 (5) :06014026. DOI:10.1061/(ASCEGM.1943-5622.0000268
[9]易岸峰.地下连续墙成槽施工泥浆重度计算方法研究[J].铁道科学与工程学报,2017,14(05):1019-1023.
[10]崔根群,刘瑶.基于槽壁稳定性的地下连续墙成槽施工泥浆重度计算方法[J].现代隧道技术,2018,55(01):178-183.
[11]周洋.软土超深地连墙成槽施工地层稳定机理研究[D].苏州:苏州大学,2019.
[12]刘杨,刘维,史培新,等.超深地连墙成槽富水软弱层局部失稳理论研究[J].岩土力学,2020,41(S1):10-18.
[13]欧明喜,戴志峰,陈颖辉,等.地下连续墙黏性土夹砂层槽壁稳定性分析[J].防灾减灾工程学报,2020,40(04):537-542.

相似文献/References:

[1]付冬平,孔剑捷,张欣亚.软土深基坑施工监测与数值模拟分析[J].华南地震,2024,(02):136.[doi:10.13512/j.hndz.2024.02.16]
 FU Dongping,KONG Jianjie,ZHANG Xinya.Monitoring and Numerical Simulation of Deep Foundation Pit Construction in Soft Soil[J].,2024,(01):136.[doi:10.13512/j.hndz.2024.02.16]

备注/Memo

备注/Memo:
收稿日期:2021-4-19
基金项目:苏州国际快速物流通道二期工程-春申湖路快速化改造工程(CSH-TJ05)
作者简介:薛青松(1986-),男,学士,工程师,主要从事隧道工程的设计和管理工作。E-mail:354677901@qq.com
通信作者:林永亮(1977-),男,博士,主要从事岩土工程等方面的研究。E-mail:lin_yliang@163.com
更新日期/Last Update: 2022-03-30